Lubrizol Bromborough

Project Outline

Turnkey demolition of former 18-acre Lubrizol Lubrication / D1 Oils Biodiesel Plant including decontamination of residual products, asbestos removal, soft strip removal and stockpiling brick and concrete arisings for on site recycling.

  • Location: Bromborough
  • Client: Ennovor Oils
  • Value: £1.1m
  • Start Date: January XXXX
  • Project Duration: 12 Months
  • Completion Date: December XXXX
  • Scrap Tonnage: 3,500 Tons
  • Aggregate Tonnage: 3,000 Tons