Astra Zeneca Avonmouth

Project Outline

Turnkey asset recovery, dismantling and traditional and explosive demolition of all above ground structures on the 100-acre former Astra Zeneca / Avara API Pharmaceuticals site. Including plant and equipment decommissioning, asbestos removal, soft stripping, ground remediation and removal of ground slabs and foundations.

  • Location: Avonmouth
  • Client: Epta Development Corporation
  • Value: £13m
  • Start Date: December 2020
  • Project Duration: 22 Months
  • Completion Date: September 2022
  • Scrap Tonnage: 18,000 Tons
  • Aggregate Tonnage: 175,000 Tons