Vauxhall Motors Luton

Project Outline

Turnkey dismantling and demolition of 11 hydraulic heavy duty tandem and spotting pressers on the live environment Vauxhall / IBC Vehicles.

  • Location: Luton
  • Client: Stellantis
  • Value: £1.5m
  • Start Date: September 2020
  • Project Duration: 6 Months
  • Completion Date: February 2023
  • Scrap Tonnage: 5,000 Tons